Metro Line - 4 (A)
Mumbai Metro Line 4A (KASARVADAVALI - GAIMUKH)
- Metro Line 4A from Kasarvadavali to Gaimukh is 2.7 km. long elevated corridor with 2 stations. It is the extension of Mumbai Metro Line-4 (Wadala – Ghatkopar – Mulund – Thane – Kasarvadavali corridor) at Kasarvadavali end.
- It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.
Length |
2.668 km (Fully Elevated) |
Line Color |
Green Line |
Stations |
2 Nos. (All Elevated) |
Elevated / Underground |
Elevated along Ghodbunder Road |
Interchange Stations |
|
Proposed Depot |
Mogharpada (Provision made in Metro Line 4 Depot) |
Project completion cost |
₹ 949 Cr. |
Daily Ridership (2031) |
1.31 Lakhs (PHPDT - 30,708) |
Present Status Updates as on 10th Feb 2025
Sr. No. | Name Of Work | Status in % |
---|---|---|
1 | PIER (Viaduct+Station upto PL) | 100% Completed. |
2 | PIERCAP EREC | 94% completed |
3 | U GIRDER EREC | 87% completed. |
4 | I GIRD EREC | 64% completed. |
5 | DECK SLAB | 60% completed. |
6 | PORTAL BEAM EREC | 90% completed. |
7 | PI GIRDER ERECTION | 100% completed. |