Metro Line - 4
Mumbai Metro Line 4 (WADALA - KASARVADAVALI)
- Metro Line 4 from Wadala to Kasarvadavali is 32.32 km. long elevated corridor with 30 stations.
- It shall provide interconnectivity among the existing Eastern Express Roadway, Central Railway, Mono Rail, the ongoing Metro Line 2B (D N Nagar to Mandale), Metro Line 5 (Thane to Kalyan), Metro Line 6 (Swami Samarth Nagar to Vikhroli).
- It shall provide rail based access to the commercial, Govt. bodies and geographical landmarks in Mumbai.
- It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.
Length | 32.32 km |
Line Color | Green Line |
Stations | 30 Nos. |
1. Bhakti Park Metro, 2. Wadala TT, 3. Anik Nagar Bus Depot, 4. Siddharth Colony, 5. Garodia Nagar, 6. Pant Nagar, 7. Laxmi Nagar, 8. Shreyes Cinema, 9. Godrej Company, 10.Vikhroli Metro, 11. Surya Nagar, 12. Gandhi Nagar, 13. Naval Housing, 14. BhandupMahapalika, 15. Bhandup Metro, 16. Shangrila, 17. Sonapur, 18. Mulund Fire Station, 19. Mulund Naka, 20. Thane Teen Haath Naka, 21. RTO Thane, 22. Mahapalika Marg, 23. Cadbury Junction, 24. Majiwada, 25. Kapurbawdi, 26. Manpada, 27. Tikuji-Ni-Wadi, 28. DongariPada, 29. Vijay Garden, 30. Kasarvadavali | |
Elevated / Underground | Fully Elevated |
Project base cost | Rs. 14,549 Cr. (Incl. Taxes and Duties) |
Ridership : | |
2031 | Daily Ridership - 12.13 Lakhs (PHPDT- 33417) |
Status as on 21.05.2023
Sr. No. | Activity | % Progress |
---|---|---|
1 | Pile | 89.2% completed. |
2 | Pile Cap | 74.8% completed. |
3 | Pier(Viaduct+Station upto CL) | 64.9% completed. |
4 | Anti Crash Barrier | 56.3% completed. |
5 | Road Restoration | 30.2% completed. |
6 | Pier Cap Casting | 73.6% completed. |
7 | Pier Cap Erection | 67.6% completed. |
8 | Stitch Concrete | 66.7% completed. |
9 | Stressing | 58.8% completed. |
10 | Bearing Pedestal | 56.1% completed. |
11 | U-Girder Casting for Viaduct | 73.1% completed. |
12 | U-Girder Erection for Viaduct | 61.4% completed. |
13 | I-Girder Casting for Viaduct | 27.1% completed. |
14 | I-Girder Erection for Viaduct | 25.5% completed. |
15 | Deck Slab Over I Girder | 25.9% completed. |
16 | U Girder Casting For Station | 37.2% completed. |
17 | U Girder Erection For Station | 31.3% completed. |
18 | Cast in Situ Pier Head for Station (Concourse level) | 59.4% completed. |
19 | Concourse Level Pier Arm Casting | 57.4% completed. |
20 | Concourse Level Pier Arm Erection | 39.8% completed. |
21 | Platform Level Pier Arm Casting | 57.5% completed. |
22 | Platform Level Pier Arm Erection | 50.2% completed. |
23 | Station L Girder Casting | 29.3% completed. |
24 | Station L Girder Erection | 27.0% completed. |
25 | Station T Girder Casting | 36.5% completed. |
26 | Station T Girder Erection | 30.3% completed. |
27 | Platform Level RCC Beam Casting | 29.2% completed. |