Overview
In order to further improve the suburban railway service network and operations, MRVC has formulated MUTP-II to be funded under the same formula as applied to MUTP-I. Government of Maharashtra and Ministry of Railway has approved the project. The Project Agreement signed on 23rd July, 2010 between Government of India and the World Bank. The Project Expenditure is shared 50:50 between the Government of Maharashtra and the Government of India.
Project cost is Rs. 5,300 crores and World Bank has sanctioned Fund of Rs. 1,910 crores.
Proposed works in MUTP – II
Sr No | Projects |
Cost |
World Bank Fund (in Crores) |
---|---|---|---|
1 | Kurla-CST 5th and 6th Lines | 659 | - |
2 | Thane-Diva additional pair of Lines | 133 | - |
3 | Borivali-Mumbai Central 6th Line | 522 | - |
4 | Extension of Harbour Line to Goregaon | 103 | - |
5 | DC to AC Conversion | 293 | 245 |
6 | EMU Procurement and Manufacture | 2930 | 1635 |
7 | Maintenance Facilities for EMUs | 205 | - |
8 | Stabling lines for EMUs | 141 | - |
9 | Technical Assistance and Institutional Strengthening | 62 | 30 |
10 | R & R | 124 | - |
11 | Station Improvement and Trespassing Control | 128 | - |
Grand Total | 5300 | 1910 |