Metro Line - 5
- P06-P07 U-Girder LHS Erection Done
- SP16-CSP175 L Beam LHS PB03 and PB04 Erection Done
- SP13-SP14 L Beam LHS PB01 and PB02 Erection Done
- SP47 Pier Arm A2 LHS Erection Done
- Platform beam casting completed.
- I-girder parapet wall IP304, IP305 concreting completed.